AI Market · Forecast desk · hit · hardware

72% · hit

NVIDIA files exhibits with the 10-Q for the quarter ended July 26, 2026 that translate the SB Energy PORTS-Pike residual-value guaranty into a per-quarter contingent-obligation disclosure and identify the OpenAI affiliate as tenant, by October 31, 2026.

Outcome

hitcalled at 72%brier contribution 0.078

NVIDIA filed the Form 10-Q for the quarter ended July 26, 2026 on August 26, 2026 — inside the window. It satisfies all three trigger elements: guarantees 'capped at a total of $105 billion' with an exposure table of $3.5B AI-cloud guarantees plus $105.0B SB Energy for $108.5B total; effectiveness conditioned on SB Energy satisfying applicable ready-for-service conditions as each of nine phases is placed in service from fiscal 2029; and the tenant identified as 'an affiliate of OpenAI Group PBC' at the PORTS Technology Campus in Pike County, Ohio. Exhibit 10.1 is the Form of Residual Value Guaranty.